Hydro Project - Rongnichu Hydroelectric Project, East Sikkim

Rongnichu Hydroelectric Project, East Sikkim

Client:- Madhya Bharat Power Corporation Ltd.

The Rongnichu Hydroelectric Project (96MW), located in the East District of Sikkim envisages utilizing the flows of the Rongnichu, a tributary of the Teesta River, for the generation of electrical power as a run-of-river hydropower development.

  • Barrage - 16.00M High above River bed level.
  • HRT - 12.58 KM long.
  • Surge Shaft - 88M deep,10.00 M finished Dia.
  • Adits (0,1,2,28 & 3) - 1860.47 m.
  • Vertical Shaft - 318M Deep, 4 M finished Dia.
  • Lower Horizontal pressure shaft - 975M Long.
  • Upper Horizontal pressure shaft - 160.80M long.